DPWH-Biliran DEO’s 2017 projects posts 67.93 percent accomplishment

Biliran DEO posts 67.93 percent accomplishment for 2017 projects with a negative slippage of 5.55 percent as of March 31, 2018......»»

Category: newsSource: samarnews samarnewsApr 28th, 2018

DPWH-Biliran DEO delivered project accomplishment ahead of the planned target as of August, this year

The District Engineering Office has sticked to its promise of fast-tracking the CY 2017 Infrastructure Projects as the district delivered 40.41 percent accomplishment ahead from the planned target accomplishmentt......»»

Category: newsSource:  samarnewsRelated NewsOct 19th, 2017

DPWH: 2017 Projects at 91.34 percent

The Department of Public Works and Highways Samar First District Engineering Office (DPWH-SFDEO) reports a 91.34 percent accomplishment on its 2017 Regular Infrastructure Projects......»»

Category: newsSource:  samarnewsRelated NewsMay 17th, 2018

Samar I registers 80.48 percent accomplishment of CY 2017 infra projects

DPWH Samar First District Engineering Office closed the preceding year with an accomplishment of 80.48 percent on all its regular infrastructure projects under the General Appropriations Act (GAA)......»»

Category: newsSource:  samarnewsRelated NewsFeb 13th, 2018

DPWH-Biliran DEO ending the year with 91.84 percent accomplishment of 2016 infra projects

DPWH Biliran District Engineering Office (BDEO) ends the year with high accomplishment posting 91.84 percent surpassing the 85 percent district target set by the DPWH Central Office......»»

Category: newsSource:  samarnewsRelated NewsFeb 23rd, 2017

Biliran DEO’s CY 2016 school building projects accomplished 33.20 percent

DPWH-Biliran is on-going on the construction of school building projects with an accomplishment of 33.20 percent as of November 30, 2016......»»

Category: newsSource:  samarnewsRelated NewsFeb 13th, 2017

Biliran DEO posts 77.06 percent of the 2016 infrastructure projects

DPWH-Biliran District Engineering Office is still in full swing in the implementation of its FY 2016 Infrastructure Projects......»»

Category: newsSource:  samarnewsRelated NewsJul 22nd, 2016

DPWH-Biliran DEO in full swing of 2018 project implementation

As of April 30, 2018, the district has an overall actual accomplishment of 16.82 percent with a positive slippage of 3.30 percent......»»

Category: newsSource:  samarnewsRelated NewsMay 19th, 2018

DPWH-Biliran DEO starts implementing the next batches of school building projects

DPWH Biliran District Engineering Office implements 76 school building projects worth P367.6M funded under FY 2017 DepEd - Basic Educational Facilities Fund (BEFF)......»»

Category: newsSource:  samarnewsRelated NewsMar 3rd, 2018

DE Adongay monitors on-going and completed FY 2017 projects

DPWH Biliran District Engineer Engr. David P. Adongay Jr. conducts inspection around the district on August 16, 2017 DPWH Biliran projects......»»

Category: newsSource:  samarnewsRelated NewsNov 2nd, 2017

DPWH-BDEO fast-tracks the construction of on-going projects

DPWH-Biliran District Engineering Office (BDEO) has completed 36 out of 57 lined-up projects under FY 2017 with a total allotment budget of P940.730M......»»

Category: newsSource:  philstarRelated NewsSep 19th, 2017

Status of DPWH-Biliran DEO’s projects, midyear of 2017

Construction is on-going for the 30 of the 57 total listing projects of the Department of Public Works and Highways (DPWH)- Biliran District Engineering office under the FY 2017 projects......»»

Category: newsSource:  samarnewsRelated NewsAug 25th, 2017

Updates on Biliran DEO’s 2017 infrastructure projects

The Department of Public Works and Highways Biliran District Engineering Office (DPWH-BDEO) is now in full swing in the implementation of its FY 2017 Infrastructure Projects......»»

Category: newsSource:  samarnewsRelated NewsJun 21st, 2017

DE Adongay inspects infrastructure projects at Maripipi Island

Engr. David P. Adongay Jr., District Engineer of DPWH-BDEO takes time to conduct a round-up inspection of Biliran DEO Infrastructure Projects at Maripipi Island, Naval, Biliran on April 28, 2017......»»

Category: newsSource:  samarnewsRelated NewsJun 17th, 2017

DPWH-Biliran DEO starts construction of CY 2017 regular infra projects

DPWH Biliran District Engineering Office (DEO) has already started its CY 2017 Regular Infrastructure project implementation with over P940M projects to complete this year......»»

Category: newsSource:  samarnewsRelated NewsMay 29th, 2017

DPWH-Biliran DEO fastracks on-going FY 2016 high impact projects

Above P40M remaining FY 2016 projects implemented by DPWH-Biliran District Engineering Office is being fast-tracked for completion until first quarter of 2017......»»

Category: newsSource:  samarnewsRelated NewsApr 1st, 2017

DPWH-Biliran DEO accomplished 90.41 percent of 2016 infra projects

The Department of Public Works and Highways (DPWH) - Biliran District Engineering Office (DEO) is fast-tracking the implementation of its 2016 infrastructure projects before the year ends......»»

Category: newsSource:  samarnewsRelated NewsFeb 13th, 2017

Gov’t speeds up spending on infra

Gov’t speeds up spending on infra Mary Grace Padin MANILA, Philippines - The government is aiming to accelerate infrastructure development this year through reforms in the procurement and implementation of projects, the Department of Budget and Management (DBM) said yesterday. In a statement, the DBM said the improved set of implementing rules and regulations of Republic Act 9184 or the Procurement Law would help expedite the launch and completion of infrastructure programs in the pipeline. Reforms in the execution of projects, such as the introduction of geo-tagging for improved project monitoring and allowing non-stop construction work to hasten project completion, will also be implemented. “The bold reforms, the pipeline of projects, the hardworking and assertive administration, and the participative citizenry – these will make the dream of making the next six years the Golden Age of Infrastructure achievable,” Budget Secretary Benjamin Diokno said. The government has allocated a total of P847.2 billion for nationwide infrastructure projects this year, up 13.8 percent from a year ago. The amount also accounted for about 25 percent of this year’s budget. Under the General Appropriations Act approved by President Duterte last December, the bulk, or P349.1 billion of the infrastructure budget was allotted to the Department of Public Works and Highways (DPWH), the Department of Agriculture, the Autonomous Region in Muslim Mindanao, and other government agencies and local government units. More than P125 billion was also granted to the Department of Education for the construction and repair of basic education facilities, primary school buildings and technical-vocational laboratories. According to the DBM, the biggest chunk of budget for road construction this year went to the road network services with P216.9 billion, 33.4 percent higher than the 2016 allocation. More than P31.1 billion was allocated for Mindanao Logistics Infrastructure Network project, which will provide highways and bridges across Mindanao to connect cities and provinces to ports and production areas. Other major road projects in 2017 include the P1.5 billion UP-Miriam-Ateneo Viaduct in Katipunan Ave., Quezon City and the P1.2 billion road widening project in the General Luis-Kaybiga-Polo-Novaliches Road, among others. The government has also allotted a total of P12.3 billion for the construction and maintenance of access roads to tourist destinations. The Department of Transportation (DOTr), for its part, will spearhead the construction of bus transport systems that are envisioned to provide efficient, comfortable and inexpensive transportation to commuters in Metro Manila and Cebu......»»

Category: financeSource:  philstarRelated NewsJan 30th, 2017

Biliran DEO’s tourist destination road project is on the verge of completion

Department of Public Works and Highways (DPWH) - Biliran DEO reports 90 percent accomplishment of its P45M Construction / Improvement of Higatangan Circumferential Road, Phase III......»»

Category: newsSource:  samarnewsRelated NewsOct 29th, 2016

DPWH completes 381 school buildings in WV

VARIOUS District Engineering Offices of the Department of Public Works and Highways (DPWH) in Region 6 completed 381 school buildings with 851 classrooms, providing a more manageable student-to-classroom ratio in the public education system of Western Visayas. The projects, which cost a total of P1.189 billion, are funded under the DPWH’s 2017 Basic Education Facilities […] The post DPWH completes 381 school buildings in WV appeared first on The Daily Guardian......»»

Category: newsSource:  thedailyguardianRelated NewsJun 8th, 2018

Clark Infrastructure Pushes Central Luzon Growth to 9.3%

Key infrastructure developments in Clark are boosting Central Luzon’s gross domestic product (GDP) which grew to 9.3 percent in 2017, almost three percent higher than the country’s GDP of 6.7 percent for the same year. Central Luzon business chambers attributed the growth to the high-impact projects under the Build Build Build Infrastructure Program including the […].....»»

Category: newsSource:  metrocebuRelated NewsMay 28th, 2018